Hive Outdoor Living
New Pool ConstructionSwimming Pool Remodelling

Hillsborough County

TampaRiverviewBrandonPlant CityValricoWestchaseView All →

Pinellas County

St. PetersburgClearwaterLargoPalm HarborPinellas ParkDunedinView All →

Pasco County

Wesley ChapelLand O' LakesTrinityBayonet PointLutzHolidayView All →

Hernando County

Spring HillBrooksvilleNorth Weeki WacheeWeeki WacheeTimber PinesBrookridgeView All →

Polk County

LakelandPoincianaWinter HavenHaines CityAuburndaleBartowView All →
What To ExpectBefore and AfterWhy Hive Outdoor Living
FeaturesTestimonialsArticles
Hive Outdoor Living
For all of your Pool, Patio and Outdoor Projects.

At Hive Outdoor Living, the #1 Greater Tampa Bay Pool Builder, our professional and diligent team is dedicated to optimize your outdoor living experience. Whether your interests are: swimming to maintain your health; having a space your children and their friends love to play in; having a gorgeous space to relax and entertain; or all of the above . . . we can make your dreams come true.

Navigation Menu
  • Home
  • Process
  • Contact us
  • Features
  • Testimonials
  • Before and After
  • Articles and News
Location Menu
  • Hillsborough County
  • Pinellas County
  • Pasco County
  • Hernando County
  • Polk County
Contact Us
  • (813) 579-2444
  • License No. CPC1458419
  • 311 S Willow Ave. Tampa, FL

Copyright © 2025 Hive Outdoor Living | All Rights Reserved

Pool Construction Process
Process

What To Expect

A clear, step-by-step guide to your pool construction journey. Know exactly what happens at each stage of your project.

Typical Construction Timeline

Most pool projects take 10-14 weeks from start to finish. Timeline may vary based on weather, complexity, and permit processing times.

10-14

Weeks Total

7

Major Phases

100%

Satisfaction

Phase-by-Phase Breakdown

Week 1

Phase 1: Initial Consultation

Meet with our design team to discuss your vision, budget, and property. We'll answer all your questions and begin planning your dream pool.

Site visit
Design discussion
Budget planning
Preliminary sketches
Weeks 2-4

Phase 2: Design & Permitting

Finalize your pool design with 3D renderings and detailed plans. We handle all permit applications and approvals with local authorities.

Final design approval
Engineering plans
Permit applications
Contract signing
Weeks 5-6

Phase 3: Excavation & Steel

Site preparation, excavation, and installation of rebar framework. Plumbing and electrical rough-in completed.

Site clearing
Excavation
Rebar installation
Plumbing setup
Week 7

Phase 4: Gunite Application

High-pressure concrete application creates your pool shell. This is one of the most exciting milestones!

Gunite spraying
Shell formation
Curing period
Quality inspection
Weeks 8-9

Phase 5: Tile & Coping

Beautiful tile work around the waterline and coping installation. Your pool starts to look finished!

Tile installation
Coping placement
Grouting
Cleaning
Weeks 10-11

Phase 6: Decking & Landscaping

Pool deck installation with your choice of materials. Landscaping and final grading around the pool area.

Deck construction
Paver installation
Landscaping
Grading
Week 12

Phase 7: Equipment & Startup

Installation of all equipment, water fill, chemical balance, and complete training on your new pool system.

Equipment installation
Water fill
Chemical startup
Owner training

What Sets Hive Apart

Clear Communication

Regular updates at every phase. You'll always know what's happening with your project.

On-Time Completion

We respect your time and stick to our schedules. No endless delays or excuses.

Quality Craftsmanship

Every detail matters. We take pride in delivering exceptional quality on every project.

Debt Free Company

Financially stable and independent. Your project is secure with a company built on solid ground.

Start Your Pool Project

Ready to Get Started?

Let's schedule your free consultation and walk through exactly what to expect with your pool project.